Project Description

Consulting services for preparing designs and tender documents and Continuous construction supervision of raw water transmission line from 6th October WTP Diam. 1000mm, and construction of the underground reservoir and a water booster pumping station to compensate water pressure in the network

Project Details

DATE

From 10/2017 to 4/2018

Holding Co. for water and wastewater & Giza water and wastewater Co.

  • Survey / Soil Researches
  • Borings Works
  • Hydraulic designs of raw water transmission line diam. 1000mm
  • Electromechanical, Architecture, structural design for underground reservoir and water booster pumping station.
  • Providing technical support during the stage of tendering, decision, and awarding.
  • Continuous construction supervision.